Work on the new terminal at Clayton J Lloyd International Airport is progressing well, with completion expected in October.

The parking lot is 85% finished, power now energised to the main distribution panel, and the elevator installed with the HVAC system set to be operational soon.

Structural and finishes works include the roof structure which is now complete with final waterproofing underway, and windows and doors fully installed to create a sealed building envelope.

In terms of passenger experience, the pre-board screening (PBS) area has been equipped with state-of-the-art CTX screening machines and a body scanner, ensuring speed, efficiency and top-tier security.